RWA System Restoration Project: Scope of Work [rev. 4]
NOTE: Work to be scheduled only as funds are available. According to NMED ALL existing meters must be replaced to install backflow prevention. Phase order is determined by potential threat to the system in the event of failure. The order within each phase may change according to ease of access.
PHASE 1: Masters, valves, and radio-read software.................................................................. $34,000.
|
|
|
PHASE 2: Fence tank [required by NMED DWB]........................................................................ $15,000.
PHASE 3: Orphaned meters [usage not visible through a master meter]................................... $11,700.
|
|
|
PHASE 4: Persistent read errors.................................................................................................. $6500.
|
|
|
PHASE 5: Homes occupied F/T or P/T; more difficult to access in snow..................................... $18,200.
|
|
|
|
PHASE 6: Homes occupied F/T or P/T; easier to access in snow................................................. $15,600.
|
|
PHASE 7: Structures or frost-frees used mainly in good weather.............................................. $29,900.
|
|
|
|
PHASE 8: Structures or frost-frees that receive intermittent or no use..................................... $27,300.
|
|
|
|
TOTAL ESTIMATED COST............................................................................................. $158,200.